Connect the delay to the project record. We organize documents, analyze schedule impacts and prepare narratives and exhibits for dispute discussions.

Delay analysis / Compare the record
Delay analysis / Compare the record exampleAs-planned and as-built dates with a delay window01 JUN08 JUN15 JUN22 JUN29 JUNAS PLANNEDAS BUILTDELAY WINDOW7 DAYSILLUSTRATIVE VARIANCEANALYSIS DEPENDS ON THE PROJECT RECORD
ExampleAs-planned and as-built dates with a delay window

01 / Deliverables

What you get

A defined package, matched to your project scope.

  • Claims documentation package (indexed and organized record set)
  • Impact summary memo + timeline of events
  • Schedule analysis outputs (method depends on contract + available data)
  • Exhibits/graphics for dispute discussions
  • Expert support materials (if included in scope)

02 / Workflow

How it runs

  1. 01

    Review the issue, contract requirements and available records.

  2. 02

    Index the documents and establish the timeline of events.

  3. 03

    Prepare the analysis, narrative and exhibits for review.

03 / Project fit

Who it’s for

Owners, contractors, subs, and project teams involved in or anticipating delay/disruption disputes.

What to send us

  • Schedule updates and as-built records
  • Meeting minutes and correspondence
  • RFIs, submittals, and change order documentation
  • Daily reports and progress photos
  • Contract documents and specifications

Tools & approach

Forensic schedule review techniques + documentation workflows (file indexing, logs, exhibit formatting) aligned to the project record.

Impacted as-planned / Time impact analysis / Windows analysis / As-built analysis

Timing

Timing depends on the issue and record volume. We confirm the scope and review schedule at intake.

Before we start

When should we engage claims consulting?

Early involvement helps preserve records while events are fresh. We can also review an existing dispute and its documentation.

Do you provide expert testimony?

We can support expert report prep and testimony coordination depending on engagement scope and jurisdictional needs.

What records help the most?

Schedule updates, meeting minutes, daily reports, change orders, correspondence, RFIs/submittals, and a clear progress narrative.

What delay analysis methods do you use?

We use industry-accepted methods including impacted as-planned, time impact analysis, windows analysis, and as-built approaches—selected based on contract requirements and available data.

Can you support mediation or arbitration?

Yes. We prepare documentation, exhibits, and analysis packages suitable for negotiation, mediation, arbitration, or litigation support.

Next / Your project

Let’s define the scope.

Tell us what you’re building, where the work stands and when you need the deliverables.

Request a Consultation

Share the scope and deadline.